Project features
A unique feature of this project is the construction of the angled tower which stands on huge pillars in the middle of the fjord. The angled structure required a system that could facilitate the transportation of material and personnel efficiently.
Safety was another concern as the transportation system needed to withstand extreme weather conditions and intense winds i.e. working winds of 80 km/h and storm winds up to 170 km/hr. Considering all these factors, Scanclimber’s SC2032-65 hoist was chosen for the project.
The tower was to be built with a curved profile, so the hoist needed to be mounted at a given counter angle to allow erection along the tower. An angled hoist base was cast. The project included a 10-stage erection process for the hoist. The hoist anchoring distance changed as the tower progressed due to the tower’s vertical curvature.
The planned height for the tower was 70 m and the hoist was installed when tower construction reached around 20 m. The hoist was a key tool in the construction of the rest of the tower. The hoist was installed at the site in Aug, 2012 and the Kåfjord bridge project was completed a year later. The bridge was opened to traffic on 20 Dec, 2013.
Project Facts | |||
---|---|---|---|
Hoist used | SC2032-65 | ||
No. of units used | 1 | ||
Payload of hoist | 2000 kg or 24 persons | ||
Height of tower | 70 m | ||
Hoist installed | August, 2012 | ||
Project completion | December, 2013 | ||
Unique features | 10 stage hoist erection |